E1: 49: Need Ability To Perform Carton Reorganization Other Than Order Creation Date Without Changing Routing Status

(Doc ID 2313099.1)

Last updated on OCTOBER 25, 2017

Applies to:

JD Edwards EnterpriseOne Transportation Management - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

When trying to reorganize cartons using P4620 for an order created yesterday (having lead days greater than order creation date) and trying to ready the shipment next day after order creation, system updating routing status to '1' in P4620 application even though  there are enough lead days for shipment preparation. Need ability to pack the shipment other than order creation date - in case the shipments were huge.