E1: 34: MRP Is Not Planning Correctly When Firm WO And Interplant Demand Exist In The Same Period

(Doc ID 2329453.1)

Last updated on NOVEMBER 20, 2017

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

MRP is not planning correctly when Firm WO and Interplant demand exist in the same period. The G and L has been removed from UDC 34/MT. There are WO and OP on a same day in the supply branch. When running MRP, an OT is created correctly in the demand branch, but WO or OP is unchanged or any new Supply is not created.