Symptoms

MFG work orders does not calculate cost of parts assigned in the final cost of the assembly

Unplanned A1 material costs for actual costed (02) work orders do not get accounted for when running R31804 because there isn't an A1 line in the F3102

Need to include A1 costs into the finished good IC

STEPS TO DUPLICATE
1. Create an Actual costed (02) manufactured item
2. Create an Actual costed (02) purchased item
3. Add a Routing for parent item but not bill of material. Parts will be
added as unplanned directly into the P31113
4. Enter a work order
5. Run R31410 to attach the routing
6. F3102 will have the B1 cost based on this
7. Issue an unplanned part
8. Run R31802A over just the work order number to process the IM's just added
9. F3102 does not get updated with an A1 line


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Unplanned issues are not accounted for in the finished good cost

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms