E1: 31: Current Costs In F3102 For X Costs Set To 0 After Deleting WO Parts List

(Doc ID 2386507.1)

Last updated on APRIL 15, 2018

Applies to:

JD Edwards EnterpriseOne Shop Floor Control - Version 9.1 and later
Information in this document applies to any platform.

Symptoms


Current Costs in F3102 for X costs set to 0 when deleting WO parts list after parts list has only been attached

The standard and current costs for X costs are established when the work order header is created and the current amounts should not be cleared when deleting the parts list.

The issue can be reproduced at will with the following steps:
1. Create Mfg work order for standard 07 cost item with rolled up X cost. Note that standard and current cost and units are written for X cost in F3102 / P31022.
2. Attach parts list and routing using R31410.
3. Using row exit from P48013 navigate to parts list. Select form exit Delete Parts List. Note that F3102 current cost has been reset to 0.



Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms