R3483 Action Orders In Date Order

(Doc ID 2393663.1)

Last updated on MAY 01, 2018

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

On : 9.2 version, MRP R3483

Orders being deferred by R3483 need to be processed in date order and order being cancelled need not get deferred first. The R3482 action messages are in date sequence. First order, in date sequence, is cancelled and later orders get defer messages. R3483 should work in sync with R3482.

Expect that the demand planning will be in date sequence, from current date thru to future date, irrespective of running R3482 or R3483.

Cause

Sign In with your My Oracle Support account