E1: 46: Planned Cross Docking Workbench (P4614) Doesn't Show All Quantities From Receipt Routing When the Receipt Was Split in Multi Location Screen(P42053) (Doc ID 2399003.1)

Last updated on JULY 16, 2018

Applies to:

JD Edwards EnterpriseOne Procurement and Subcontract Management - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

P4614 (Planned Cross Docking Workbench) does not show all the quantities from receipt routing when the receipt is split using Multi location screen P42053 .

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.Set Cross Docking Supply = 1(Purchase Order types) in P40040 (Document Type Revision) for doc type OP(Purchase Order).
2.Create an Item and select Cross-Docking in the Item master P4101 and P41026 Item Branch , tab Additional Info.
3.Set a route in Receipt Routing Definition (P43091)
4.Set a Receipt Routing for the Cross Docking Item in P43090 and for a Supplier .
5.Create a purchase order for this Supplier and Cross Docking Item .
6.Set processing options for P4210 , tab 5- Commitment , 1. Activate Availability Checking = 2 (Activate, notify, but do not backorder or cancel )
7.Enter a sales order for the Cross Docking Item .
8.Check in P4614 Cross Docking workbench to ensure that both PO and SO are updated correctly.
9.Set 2 versions for P4312 with Processing options :
 Version 1 of P4312 , Tab 13-Cross Docking, 1.Cross Docking = Blank
  Tab 4-Process , 11.Receipt Routing = 1 (Activate Standard)
 Version 2 of P4312 , Tab 13-Cross Docking, 1.Cross Docking = 2 (Use Planned)
  Tab 4-Process , 11.Receipt Routing = Blank
10.Set P43250 (Routing Statuses) to call the P4212 version 2 (APV2P43120).
11.Receipt the purchase order using P4312 version 1 (APV1P43120), using Multi location screen in P42053 and split receipt in 3 lines for 3 lot number.
12.Check again in P4614 Cross Docking workbench and see that the application does not show all the receipt split lines , only first line.
In this case , it cannot associate the sales order with the lines of the Purchasing Order .

P4614 (Planned Cross Docking Workbench) has to show all the quantities from receipt routing when the receipt is split using Multi location screen P42053 .

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.