E1: 34: Supply and Demand Inquiry (P4021) Not Respecting Planning Fence Rule C as the System is Calculating Forecasts within the Inside of the Fence
(Doc ID 2421445.1)
Last updated on FEBRUARY 08, 2024
Applies to:
JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
EnterpriseOne 9.2
When viewing an item with a defined Planning Fence Rule of C (Customer Demand before the fence/Greater of Forecast or Customer Demand after the fence), forecast quantities within the defined Planning Fence are being subtracted in the Supply & Demand Inquiry (P4021). On the inside of the fence, only Customer Demand should decrement Quantity Available. This appears to have have changed after applying 9.2 Update 2 and going code current on April 1, 2018. This presents an erroneous Quantity Available in P4021 although MRP Messages are not based on the Supply & Demand Inquiry.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |