JDE1: 51: Forced Adjustments Not Calculating Correct EAC Value - Must Run R51803 (Doc ID 2451486.1)

Last updated on JULY 21, 2020

Applies to:

JD Edwards EnterpriseOne Project Costing - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

On : 9.2 version, Project Costing

ACTUAL BEHAVIOR
---------------
When making an adjustment in the P510211 to an account with a MOC=S, the system is not correctly recording changes. The result is that they are required to run the R51803 to get correct values for the projected final amounts.

EXPECTED BEHAVIOR
-----------------------
The P510211 should correctly update the projected final ledger for all accounts (including those with MOC=S).

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Add a new job and add accounts and budgets
2. Make sure that two of the accounts where budgets are added have a MOC=S.
3. View projected final values in the JSI
4. Using the P510211, make an adjustment to one of the cost accounts with a MOC=S so that it is larger than the budgeted amount.
5. View projected final values on that account and see that they are not corrected - they were not updated by the amount of the adjustment in step #4.
6. Run R51803 and then view results on JSI. Note that the projected final values are now correct.
7. Client shouldn't have to run the R51803 to get the correct projected final values for accounts with MOC=S

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot get correct projected final values that will affect Profit Recognition.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.