Purpose
Frequently asked questions regarding processing retainage at Voucher Match / Match Voucher to Open Receipt (P4314)
Questions and Answers
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Purpose |
Questions and Answers |
Question 1: Is it possible for flex accounting to be used in conjunction with the Retention AAI? |
Question 2: Is it possible to cancel the retained amount in a purchase order (PO, P4311) at the time of voucher match (P4314)? |
Question 4: How is the exchange rate determined for the retained amount? |
Question 8: Which tables store retainage information? |
Question 9: Can retainage be tracked at individual invoice level? |
Question 10: Tax distribution is wrong for a purchase order with retainage. Orders without retainage seems to be OK. Why? |
Question 11: The AAI PCRETN is not pulling the correct business unit when using projects, why? |
Question 12: Is it possible to enter both the progress payment and release retainage at the same time? |
Question 13: Voucher has been reversed after the retainage was paid. What is the best way to settle the accounts with no option for reversal of payment? |
Question 14: The retainage records are not found when trying to release retainage. However, the F4311T and F43121T tables are populated correctly. What could be causing this? |
Question 15: In Release 9.0, the when releasing retainage the Gross Amount field is not being populated automatically. What could be causing this? |
Question 16: Can the retainage percentage default from the Supplier Master (P040412)? |
Question 17: Can a progress payment and release of retainage be done at the same time in a single step? |
Question 18: What does the 'Apply Retainage' check box do in the line type settings? If we are doing a PO with that box checked for line type J vs unchecked, is there any difference in processing? |