Symptoms

The requested date in PO Generator (P43011) is calculated based on the average lead time of the item. If this date is calculated as a non-working day in the P00071 (work day calendar), are warning message is displayed, Requested Date Is Not a Work Day (Error 1921). 

The requested date should move to the nearest future working day based on the work day calendar setup. For example, if an item is setup with four lead time days and the requested date falls on a Sunday, the customer would like for the requested date to be automatically moved to the following Monday or first available future working day.

The current workaround for this issue is to have the user manually update the requested date in the P43011 to make it a valid working day.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.