E1: 31P: P31P001 Cancel Task Retains Planned Amounts
(Doc ID 2618916.1)
Last updated on DECEMBER 10, 2019
Applies to:
JD Edwards EnterpriseOne Engineer to Order - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
Cancel task does not remove planned costs. A production work order task, with an attached parts list, shows planned costs coming from the attached parts list and routing. When the task is cancelled, without first removing the parts list or routing, the planned costs are unchanged.
The issue can be reproduced at will with the following steps:
Select an existing parent bill of material item setup for ETO or create a new item.
Add a discrete accounting ETO project and add the ETO parent (G, S) item as a production task.
Process task or process project to run R31410.
Confirm that the financial tab is now populated with the planned costs written to the F3102.
For the production task, select the more task actions, cancel.
Review the F3102 and planned amounts. Planned Amounts remain. This is incorrect.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|