MRP Not Planning Correctly Manufactured Item With Short Shelf Life (Doc ID 2734406.1)

Last updated on MARCH 12, 2021

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

MRP is not considering the shelf life of manufactured items when suggesting creation of work orders.

Steps to reproduce:
1. Setup a manufactured item with a short shelf life (i.e. 5 days) and a minimum order quantity of 20.
2. Enter a forecast for the manufactured item for a quantity of 10 on day 5, another quantity of 10 on day 15 and another quantity of 10 on day 30.
3. Run MRP

Check that the order messages is only for a quantity of 20 on day 5 and then another for a quantity of 20 on day 30, instead it should plan for orders on day 5, 15 and 30 for with a quantity of 20 each.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.