E1: 34: Master Planning Schedule - Multiple Plant (R3483) Creates Over Supply When Using Periods of Supply (OPC = 4) Frozen WOs and Minimum / Multiple Quantity (Doc ID 2798794.1)

Last updated on AUGUST 12, 2021

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

For min/multiple quantities and OPC = 4 frozen WO, Master Planning Schedule - Multiple Plant (R3483) is creating over supply.

Issue can be replicated following these steps:

1. In P41026 Item Branch, create a manufactured parent item with Multiple Order Quantity = 50 and OPC = 4, OPV = 5. In P3460 Work With Forecasts, create demand (as FCST) for 500 EA, 2 days in the future from the MRP run date. And another FCST for 120 EA 10 days in the future.
2. In P48013 Manufacturing Work Order Processing, create a frozen WO as supply for 600 EA, 7 days into the future.
3. Run Master Planning Schedule - Multiple Plant R3483. In MRP/MPS Detail Message Revisions P3411, notice the suggested planned WO is for 150 EA, instead of 50 EA.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution