E1: 34: MRP Requirements Planning Time Series (P3413) With Forecast Consumption Displays with Past Due 2 Where the First Date Period is Expected (Doc ID 2824053.1)

Last updated on SEPTEMBER 28, 2024

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Goal

To explain why on some dates, Requirements Planning (MRP/DRP) (R3483/R3482) may generate a Time Series (P3413) where the Past Due 2 is actually the Generation Date of MRP and the first period with a date is the following day.