My Oracle Support Banner

E1: 34: MRP Requirements Planning Time Series (P3413) With Forecast Consumption Displays With Past Due 1 Where the First Date Period is Expected (Doc ID 2824053.1)

Last updated on APRIL 17, 2023

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Goal

To explain why on some dates Requirements Planning (MRP/DRP) (R3483/R3482) may generate a Time Series (P3413) where the Past Due 1 is actually the Generation Date of MRP and the first period with a date is the following day.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.