E1: 31: In P31115 Co/by Completion Revision, the Completed Quantity Is Rounded up to a Bigger Quantity
(Doc ID 2828352.1)
Last updated on APRIL 04, 2025
Applies to:
JD Edwards EnterpriseOne Shop Floor Control - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
With a process and CO item, for specific WO quantities (105 and 150 PL), when completing a partial of 1 PL, the resulting quantity in P31115 CO/BY Completion Revision is bigger with a few decimals than when completing a 1 PL WO.
Steps:
- Create a Process Item P40792 and a Co Item 40792. Both items have a UOM Conversion of 1 PL = 12200 EA. For Process, the Production UOM = PL and for the Co, the Production UOM = EA.
- When creating a work order for 1 PL and completing 1 PL with P31114, the system suggests to complete 12200 EA in P31115.
- When creating a work order for 100 PL and completing 1 PL with P31114, the system suggests to complete 12200 EA in P31115.
- When creating a work order for 105 PL and completing 1 PL with P31114, the system suggests to complete 12200,0006 EA in P31115.
Additional info:
In the occasion that an item was used that has a different number of EA stacked on a pallet, the order quantity of 105 PL will not be a problem.
Customer has also seen the same behaviour with the order quantity of 150 PL for an item with UOM 12200 EA per pallet.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |