Symptoms

Firm supply orders in the demand plant should be considered before net new transfer orders. Multi-plant MRP R3483 Planning creates P3411 C Cancel action messages for the firm supply orders in the demand plant and generates net new Planned (PLO) OT/ST Transfer Orders.

STEPS TO REPRODUCE
==================

  1. Setup P41026 multi-plant planning data items, with and w/o freeze fence (FF) days, OPC 1 lot for lot.
  2. Create matching P4210 SO demand and P4310 OP purchase supply or P48013 WO supply in demand plant in past due, inside freeze fence, and in future dates.
  3. Create P3403T Branch Relationship records with availability check (AVLC=0) not enabled and run R3483.
  4. Review P3413 Time series and P3411 messages.
  5. Run R3483 and note that firm supply orders outside of freeze fence gets C Cancel P3411 action messages.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.