E1: 43: Open Commitment Amount in Encumbrance Inquiry (P40230A) After Cancelling Open Purchase Order Line in PO Entry (P4310)
(Doc ID 2849866.1)
Last updated on APRIL 04, 2025
Applies to:
JD Edwards EnterpriseOne Procurement and Subcontract Management - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
When reviewing a purchase order line that was canceled in the Commitment Inquiry (P40230A), an open commitment is still showing for the amount on the order line. This happens when the order was vouchered, then the voucher was reversed and the line was canceled.
The issue can be reproduced at will with the following steps:
1. Enter a purchase order (P4310) for a J line type that will create a commitment.
2. Voucher match (P4314) the line in full and post to relieve the open commitment.
3. Reverse the voucher (P4314), but do not post the reversal.
4. Cancel the purchase order line using the P4310.
5. Post the reversal. The amount committed still appears in the P40230A.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |