E1: 34: LANG: Processing Options Templates T3482, T3483 are Missing Additional Strings for Spanish Language Translation
(Doc ID 2944468.1)
Last updated on MAY 16, 2023
Applies to:
JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
Several processing options were added as part of Enhancement Bug 31400608 under feature "Lot Dates Support for Requirements Planning" (Feature ID 24565) and this feature was marked with "Yes" for all applicable translation languages.
However, both R3482 - MRP/MPS Requirements Planning and R3483 - Master Planning Schedule - Multiple Plant UBEs are still showing only 2 options available in the tab 3For instance, the processing option # '1. Include Lot Dates' in the tab '3-On
Hand Data' of R3482/R3483 UBEs has 10 different options on the latest JDE code, when using English language, but the latest version has only 2 options available to choose from when using Spanish language.
Steps:
- P0085 - Open My System Options
- P0085 - In the Display Preferences form, set the Language to S - Spanish
- Log out from JDE and then log into JDE
- BV - R3483 - Select a standard MRP version (e.g. ZJDE0004) and review the processing options
- R3483 - 3-Dados Existentes (3-On-Hand) tab, note that the processing option # 1. Inclusion de fechas de vencimiento de lotes (Include Lot Dates) only displays 2 options available:
En blanco (blank) = No incluir (do not include)
1 = Incluir (include) - Review the same processing options for a standard version of R3482 and note the exact 2 options as above
- P0085 - Open My System Options > Display Preferences form - Set the Language to the blank (default) value, available for English language
- Log out from JDE and then log into JDE
- BV - R3483 - Select the same standard MRP version (e.g. ZJDE0004) and review the processing options available
- R3483 - In the 3-On-Hand tab, processing option # 1. Include Lot Dates provides 10 options available to choose from:
blank = do not include
1 = lot expiration date
2 = sell by date
3 = best before date
4 = user defined date 1
5 = user defined date 2
6 = user defined date 3
7 = user defined date 4
8 = user defined date 5
9 = commitment date method from item/branch master - BV - R3483 - In the 3-On-Hand tab, processing option # 1. Include Lot Dates also provides 10 options available, the same as above
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |