E1: 30: 31: R30812 Cost Simulation Divides Routing Costs by Accounting Cost Quantity (ACQ) When Time Basis Code (TIMB) is Set to 0 (zero) "Fixed Time Basis"
(Doc ID 2957147.1)
Last updated on OCTOBER 29, 2024
Applies to:
JD Edwards EnterpriseOne Product Data Management - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
The Cost Simulation R30812/R30825 calculates costs based on the Routing values divided by Accounting Cost Quantity (ACQ). When ACQ is greater than 1 this appears to understate the costs per unit.
The issue can be reproduced at will with the following steps:
- Item Branch record (P41026) is set up with TIMB "Time Basis Code" = 0
- Routing (P3003) steps are set up with TIMB = 0
- Item is set up with Accounting Cost Quantity >1
- Run R30825 to calculate the simulated cost
- Review Cost Components and note B1 is calculated as Run Labor divided by ACQ
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|