E1: 34: R3483 Multi Branch Plant Planning UBE Cancels Existing Purchase Order (OP) Supply and Generates New Order Messages in P3411 MRP Messages Program to Satisfy Demand Orders. (Doc ID 3054397.1)

Last updated on OCTOBER 23, 2024

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

R3483 MRP cancels an existing purchase order (OP) message and suggests a new order & expedite (B) message in P3411 MRP messages to satisfy demand quantities.

Steps:

1) P4101/P41026 - An Item setup with Order Policy Code = 4, Value = 50 days, safety stocks (50 units) and min order quantity (100 units).
2) P4310 - Create a purchase order for a quantity of 100 units.
3) R3483 - Setup and run MRP.
4) P3411 - Review and observe that MRP cancelled an existing purchase order message and suggested a new B - order and expedite message.

Changes

Issue started after applying fix in Bug 36701715

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.