E1: 34: R34410 How to Release Multiple Shipments Per Day (Doc ID 642990.1)

Last updated on MAY 12, 2017

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version XE and later
Information in this document applies to any platform.
System Code: 34-Requirements Planning
R34410 - Supplier Schedule Release Generation
B3401155 - SRS Release Schedules


Goal

Information Center: Overview of JD Edwards EnterpriseOne Requirements Planning > Information Center: Using JD Edwards EnterpriseOne Requirements Planning > Note 642990.1

This document will give users using Supplier Release Schedule, methods on how they can release orders, one per shipment from supplier, even if two shipments are to be made on the same day. (Volume / size requirement and cross border paperwork).

Standard functionality is for SRS to consolidate all orders into one PO/ PO Line at time of release.

Example:
A client imports motors from Canada and orders 300 of them at the same time. Rather than receiving one PO for 300, it is desired to create 3 POs for 100 motors to accommodate the truckload.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms