My Oracle Support Banner

E1: 34: P3411 / R3411 MRP Message Detail FAQ (Doc ID 651219.1)

Last updated on DECEMBER 14, 2018

Applies to:

JD Edwards EnterpriseOne Apparel Management - Version 9.0 and later
JD Edwards EnterpriseOne Engineer to Order - Version 8.9 and later
JD Edwards EnterpriseOne Requirements Planning - Version XE and later
JD Edwards EnterpriseOne Capital Asset Management - Version XE and later
Information in this document applies to any platform.
System Code: 34-Requirements Planning
P3411 - MRP/MPS Detail Message Revisions
R3411 - MRP/MPS Detail Message Processing
P3401 - Message Summary
P48013 - Manufacturing Work Order Processing
P03013 - Customer Master



Purpose

This document supplements  E1: 34: P3411/R3411 MRP Detail Messages - Understanding and Use Document 625973.1.  It provides answers to questions not covered in other documentation for MRP Detail Messages (P3411) and processing (R3411). 

Having issues with messages?  Refer to E1: 34: MRP Not Planning Correctly or S&D P4021 Appears Incorrect FAQ Document 641434.1 and E1: 34: P3401, P3411 & R3411 Error IDs, Causes and Steps to Correct Document 639653.1 for other symptoms and solutions.

Questions and Answers

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Questions and Answers
 Question 1:  Why are P3411 and R3411 Not Including Transfer Leadtime for OT Messages?
 Question 2:  When the shipment is routed within the Transportation module, the ST does not have a backscheduled Pick Date
 Question 3:  Why aren't Action Messages within Detail Messages (P3411) updating the work order (WO) with the new quantity or date? 
 Question 4:  When demand moves, and the supply for that demand is still needed, why does it defer it over the next demand in line?
 Question 5:  How are the MRP planning fence, Freeze fence & Message display fence days are counted?
 Question 6:  MRP is creating multiple work order messages (O type) in the MRP Detail Messages (P3411 or P3401 Family Review) with the same due date.
 Question 7:  Does MRP consider lot grade in the lot master of lots on hand when netting requirements?
 Question 8:  Why is MRP not suggesting to use existing on-hand quantity in supply branch?
 Question 9:  Receiving 'Lead Time is Zero' message even though Level Lead time is set up?
 Question 10:  Can MRP plan for component items based on parent item MRP messages added in P3411 from an external system?
 Question 11:  What is the difference between WP and WO messages?
 Question 12:  When processing messages, how does the system know what status to use when creating the purchase order, transfer order or work order?
 Question 13:  Can MRP (R3482/R3483) planning lot for lot create planning message for the lot / location needing replenishment?
 Question 14:  Why does MRP suggest planned orders (PLOs) for Capital Asset Mmgt work orders?
 Question 15:  Is it possible to add an attachment to an order message in P3411?
 Question 16: Is there a way to permanently remove MRP generated messages that doesn't need any action?
 Question 17: Why deleting 'E - Expedite' message from UDC 34/MT does not prevent MRP from generating E - expedite messages in P3411 MRP messages program?
 Question 18: Is it possible to generate a consolidated purchase order (PO) number without closing the P3411 application?
 Question 19: Why is MRP generated ST order for Kit parent item does not display corresponding Kit component items when inquired in P4210 program?
 Purchasing Related
 Question 1:  Is it possible to create purchase orders on a parent kit item by processing MRP messages?
 Question 2:  P4310 'PROV' field is being marked with '1' after processing a G message with P3411?
 Question 3:  Can a components PO Requested Date be backscheduled without changing it's Start Date on the WO Partlist?
 Question 4:  Processing messages for purchase orders on SC line type items, the PO lines are 'S' line type & account numbers are incorrect?
 Question 5:  Why Processing OT messages in P3411 takes long time?
 Question 6:  Only the first line on each OT & ST order have a unit and extended cost/price, when Consolidation used?
 Question 7:  When attempting to process a purchase order O - Order message or a B - Order & Expedite message, Error: 0280, Status Invalid for this Order Type occurs?  
 Question 8:  Why doesn't P3411/R3411 process a purchase order message successfully to create purchase orders?
 Question 9:  Why is R3411 defaulting start date and request date as today's date when processing a order message with recommended completion date in the future?
 Question 10:  What are the mandatory fields to be populated inF3411 to run R3411 successfully?