E1: 31P: ETO Project Cost Rollup (Doc ID 865105.1)

Last updated on DECEMBER 20, 2022

Applies to:

JD Edwards EnterpriseOne Engineer to Order - Version 8.12 and later
Information in this document applies to any platform.
In the Project Workbench application (P31P001), the system does not display the actual costs of the project implementation. Review the Master Work Order File (F4801), where the activities are stored, identify the fields in the actual material, labor real, real costs and real total, and note that it does not display the actual cost information.

Program ID/Object: P31P001
Application and/or Tools Release: 9.96


Goal

The actual costs for production and non-production tasks must be rolled up in order to accumulate the actual costs of the project.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
 Production Costs
 Standard Cost Completions
 Actual Cost Completions
 Purchase Costs
 Non Production Costs
 Mapping Cost Classifications
 Units Not Completed Error in Work Center When Running R31802A