E1: 31/34: MRP Ignores "Line Item Closed" Quantities in WO Parts List (R3482/R3483/P3111) (Doc ID 972610.1)

Last updated on NOVEMBER 17, 2016

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version XE and later
JD Edwards EnterpriseOne Shop Floor Control - Version XE and later
Information in this document applies to any platform.
System Code: 31-Shop Floor Management
System Code: 34-Requirements Planning
R3482 - MRP/MPS Requirements Planning
P31113 - Work Order Inventory Issues


Symptoms

Information Center: Overview of JD Edwards EnterpriseOne Shop Floor Control > Information Center: Troubleshooting JD Edwards EnterpriseOne Shop Floor Control > Document 972610.1
Information Center: Overview of JD Edwards EnterpriseOne Requirements Planning > Information Center: Troubleshooting JD Edwards EnterpriseOne Requirements Planning > Document 972610.1

MRP (R3482/R3483) calculates supply and demand for MRP items based on Open Work Order Statuses.  Some MRP items have lot numbers.  When material issues (IM) to work orders are split between lines to account for different lot numbers, only the first line (not the "Line Item Closed" line) is taken into account for MRP demand.  All issued quantities on "Line Item Closed" lines are ignored in for MRP demand calculations, creating "false" demand on MRP items with lot numbers.

Changes

Use of unplanned issues.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms