WS: 31 Start Dates Between Work Order Header and First Operation Sequence of Routing Do Not Match with Outside Operation on Routing P48013 (Doc ID 1926046.1)

Last updated on AUGUST 17, 2016

Applies to:

JD Edwards World Shop Floor Management - Version A9.3 cume 1 and later
Information in this document applies to any platform.

Symptoms

The Start Dates between the work order header (P48013) and the first operation sequence step of the routing (P3112) do not agree. This occurs for Variable leadtime items. When an outside operation is present on the routing, the start dates no longer agree.


Cause