WS: 34: MRP P3482/P3483 Duplicates Phantom Component Demand (Doc ID 2014780.1)

Last updated on OCTOBER 09, 2015

Applies to:

JD Edwards World Material Requirements Planning - Version A9.3 cume 1 to A9.3 cume 1 [Release A9.3]
Information in this document applies to any platform.

Symptoms

Running MRP (P3482/P3483) in A9.3.1 produces erroneous planned order messages in Supply & Demand (P4021) and can display for the same day repeatedly. The items where the messages are generated are phantom items.