Symptoms

Completing active Item PM Schedule using the PM History & Completion (P12071) erroneous Schedule Date (TDT) and Projected Start Date (PNST) populated in the new status 01 Item PM Schedule when using Frequency Indicator (FRIN) 6 and Last Completed Date is 10/31/16. Last Completed year does not matter. With the 10/31/16 date the new Status 01 Item PM Schedule date was populated with 04/27/43.

Cause