ODI Scheduler 'Interval for Repetitions' Field Settings Giving Unexpected Launch Times.

(Doc ID 1097560.1)

Last updated on AUGUST 31, 2016

Applies to:

Oracle Data Integrator - Version and later
Information in this document applies to any platform.


An ODI Scenario has been scheduled to run four times per hour,  for example from 10:00am and do repeats every ten minutes. This would mean that the Scenario should be launched at the following times :

However, on observation the launch does not take place every ten minutes as expected.

The first run is starting at 10:00 as expected but the remaining sessions starting not with a 10 min delay. On Operator it shows the following start time: