SOA 11g: SCA Unit Test Run does not Complete Until Timeout Reached
(Doc ID 1555494.1)
Last updated on APRIL 23, 2019
Applies to:
Oracle SOA Suite - Version 11.1.1.1.0 to 11.1.1.7.0 [Release 11gR1]Information in this document applies to any platform.
Symptoms
On : 11.1.1.6.0 version, BPEL Service Engine
ACTUAL BEHAVIOR
---------------
When using "Unit test", run does not show completed in Enterprise Manager until the timeout is reached, even if the actual test case completes much faster.
EXPECTED BEHAVIOR
-----------------------
The Enterprise Manager console shows the task completed as soon as the composites have completed
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a echo dummy project (sync) with test suite
2. Deploy and, on enterprise manager run the test suite
3. The console takes much more time to update than the actual composite does.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |