SOA 11g: Date is Always Set to 1 Month Higher than what is Set for the Message through the MQ Adapter (Doc ID 1566081.1)

Last updated on JULY 02, 2013

Applies to:

Oracle SOA Platform - Version 11.1.1.6.0 and later
Information in this document applies to any platform.

Goal

Date in MQ is always set one month higher than what is set in the message
Bug No. 13435861


The date set in the MQMD Header is based on the Gregorian Calender and is always one month ahead of that set in the message.


Solution