Symptoms

ACTUAL BEHAVIOR
In a page using the dvt:timeline component the start and end dates are based on the oldest and newest item in the timeline, the timeline renders fine for the first item, but the timeline of the subsequent item is not rendered properly if the next item has different boundaries respect the previous one.

The rendering is working fine with fixed start and end dates for all items, but this is not an acceptable use case.

EXPECTED BEHAVIOR
When refreshing timeline data the rendering should be coherent.

Cause