Resource Provisioning Order for Resource Which is Dependent on Another Resource (Doc ID 2145031.1)

Last updated on JUNE 05, 2016

Applies to:

Identity Manager - Version 11.1.2.2.7 and later
Information in this document applies to any platform.

Goal

Scenario: Suppose there two different Access Policies (AP):


The problem is how to make Custom Resource1 resource to be provisioned only after Active Directory and Exchange Server resources are provisioned?

There is no functionality that access policies should be triggered in a order while executing the "Evaluate User Policies", then how to provide the order for the Access policies to provision resources as like above mentioned ?
 

Solution