Active ODI Scenario Schedule Shows Red Icon Status
(Doc ID 2173342.1)
Last updated on JANUARY 27, 2023
Applies to:
Oracle Data Integrator - Version 12.2.1.2.0 to 12.2.1.2.6 [Release 12c]Information in this document applies to any platform.
Symptoms
In Oracle Data Integrator (ODI) 12c, the Scenario Schedule status does not match the "Status" icon:
- When the Schedule is "Active", a red icon is shown in the ODI Operator > "Load Plans and Scenarios" view > Scenario name > Scheduling:
- When the Schedule is "Inactive", a green icon is shown in the ODI Operator > "Load Plans and Scenarios" view > Scenario name > Scheduling:
- When the Schedule status is "Active for the period", a correct, green icon is shown:
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |