BPM 12.2.1.2.0 is not generating Event Process Metrics on BAM 11.1.1.7.0 Data Objects

(Doc ID 2329557.1)

Last updated on NOVEMBER 21, 2017

Applies to:

Oracle Business Process Management Suite - Version 12.2.1.2.0 to 12.2.1.2.0 [Release 12c]
Information in this document applies to any platform.

Symptoms

 BPM 12.2.1.2.0 Server is not properly generating Event Process Metrics information into BAM 11.1.1.7.0 data objects. Issue happens as soon the BPM Server is bounced.

When it is deployed/redeployed the BPM Composite the issue will not occur.

After BPM Composite is deployed from Jdeveloper and executed the Event Process Metrics are generated, but as soon the BPM Server is bounced, the Event Process Metrics are not being generated.
Exception Generated on out file:

 

Cause