Include Task History Form Is Not Enabled In JDeveloper BPEL Designer

(Doc ID 455349.1)

Last updated on SEPTEMBER 08, 2008

Applies to:

Oracle(R) BPEL Process Manager - Version: 10.1.3.1 to 10.1.3..3
This problem can occur on any platform.

Symptoms

The "Include task history from", of the Advanced tab in Human Task activity, is not enabled in JDeveloper BPEL Designer.

Steps to re-create the issue :

1. Include a Human Task in a scope.

2. Include a second human task in a second scope.

3. Go to "Advanced" tab of second Human Task.

4. The "Include task history from" option is not enabled.

Cause