Why Assign Activity Or Transform Activity are Not Visible in Flow View and Audit View of BPEL Console. (Doc ID 728247.1)

Last updated on SEPTEMBER 08, 2008

Applies to:

Oracle(R) BPEL Process Manager - Version: 10.1.2.3 to 10.1.3.3.X
Information in this document applies to any platform.

Goal

This document explains why assign activity or transform activity within the same scope of a BPEL project are not visible in flow view and audit view, of the executed process, in BPEL console.

To better understand the issue please have a look at the attached Fig.doc at Fig1.0, Fig1.1 and Fig1.2.

In Fig1.0 you will notice a BPEL project that contains one transform activity followed by two assign activity.

In Fig1.1 you will notice only the transform icon is visible and

in Fig1.2 you will notice that  only Transform_1 heading is visible and three updated variable statement below it. No assign activity heading is shown.

This same behavior, only the first assign or transform activity's name or icon is displayed, can be seen if you are using more then one assign activity continuously within the same scope or more then one transform activity continuously within the same scope or have a mix and match as the above example.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms