NO PLANNED ORDERS GENERATED FOR SOME ITEMS IN MRP/DRP PLAN (Doc ID 1068359.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Materials Requirement Planning - Version 11.5 to 12.1 [Release 11.5 to 12.1]
Information in this document applies to any platform.

Symptoms

Checked for relevancy 16-May-2013

11.5 to 12.1 in Production and Test

PROBLEM
-------------
Item XX is not being planned in our DRP plan.
We run MDS into an Supply Chain MPS plan
Then have MDS as demand and MPS plan as supply for our Supply Chain DRP plan.

Support Note - Other valid scenarios:
1. The plan could be Supply Chain MRP instead of DRP plan
2. If using single org MRP, then MDS is use for MPS plan, which is then the Demand Schedule for the MRP plan.

STEPS
--------
Run plans and review results and find that this item is not planned in the DRP plan.


BUSINESS IMPACT
----------------------
cannot plan for this item successfully.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms