Relationship Lag Is Less Than Expected When An MPX Is Imported Into P6. (Doc ID 1073111.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 7.0 and later   [Release: 7.0 and later ]
Primavera P6 Professional Project Management - Version: 7.0 and later    [Release: 7.0 and later]
Microsoft Windows (32-bit)

Symptoms

Relationship lag is incorrect when a project is imported from Microsoft Project. Activities whose relationships have lag, have different early and late dates in P6 when compared with the same activities in Microsoft Project.

Cause

Sign In with your My Oracle Support account