The Actual Finish is Removed after Changing the At Completion Units For A Completed Activity (Doc ID 1083398.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera P6 Professional Project Management - Version: 5.0 and later    [Release: 5.0 and later]
Primavera Contractor - Version: 5.0 and later    [Release: 5.0 and later]
Information in this document applies to any platform.

Symptoms

The Actual Finish from a completed activity is removed when the At Completion Units are changed.

Cause