Safety Stock Numbers Higher Than Expected For Period Buckets (Doc ID 1124054.1)

Last updated on SEPTEMBER 09, 2016

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1 and later
Information in this document applies to any platform.
***Checked for relevance on 25-Apr-2013***

Symptoms

Dynamic Safety Stock calculated by the plan is incorrect.

For example: for an Item with average monthly demand is around 20,000 to 25,000 and with a safety stock set at 92 bucket days(4 months) and 4600%, you would expect safety stock about 2 months of demand around 40,000 to 50,000, but the safety stock of 66,000 to 76,000 in few months/buckets was not expected.

Cause