MRP Item Is Snapshotted And Planned In The MPS Production Plan (Doc ID 1255184.1)

Last updated on SEPTEMBER 09, 2016

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

When running a production plan the MRP Planned items are also getting planned in the plan.

This started happening after moving to 12.1.2 CU# 6 which is VCP 12.1.3.

STEPS:
1. Navigate to Responsibility > Advanced Supply Chain Planner.
2. Run A production plan
3. The output shows MRP Planned items being planned in the production plan.

Cause