Symptoms

11.5.10 in Production
with patch 6988176

PROBLEM
-------------
ATP 24x7 did not switch plans.
Log file shows
MSC_ATP_PDS_SUMM module: ATP Post Plan Processing
.........
----Done Printing Records ----
---------Before calling schedule---------
Exception in call to Call_Schedule
Return Status : S
Error Message : User-Defined Exception
Unexpected Error. Sync Call To ATP failed
Sync Error: Unable to continue further
------- Update_Summary_Flag -----
Plan ID : 21 Status : 7
ATP Status Flag Update : S
----------------End Call Synchronize-------------

STEPS
--------
Run normal 24x7 ATP plan.

EXPECTED BEHAVIOR
----------------------------
plan switch will occur and errors will not be reported in the log file.

BUSINESS IMPACT
----------------------
Plan not synced properly for all orders.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.