Remaining Units/Time Does Not Import Correctly From Excel For New Resource Assignment (Doc ID 1264122.1)

Last updated on JUNE 04, 2012

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
Information in this document applies to any platform.
***Checked for relevance on 04-Jun-2012***

Symptoms

When adding a new resource assignment, the Remaining Units/Time (remain_qty_per_hr) always imports from Excel as 1.00h/h regardless of the value entered in the XLS spreadsheet and the Default Units/Time in the Resource Dictionary.

Cause