My Oracle Support Banner

Problems Adding Tasks to a Provisioning Plan with Backdated Tasks. (Doc ID 1323997.1)

Last updated on FEBRUARY 28, 2019

Applies to:

Oracle Communications MetaSolv Solution - Version 6.0.15 to 6.2.0 [Release 6.0.15 to 6.2.0]
Information in this document applies to any platform.
Work Management Setup > Provisioning Plans > Task Dependencies & PERT Chart tabs


Symptoms

Users reported problems when adding tasks after the DD task to a Provisioning Plan that has backdated or backward facing tasks.
Adding a task to such  provisioning plans, and changing its dependencies, changes the backward dated tasks to (normal) forward dated tasks.

Also if you added a dependency from the DD task to another task via the PERT chart then all the backward facing tasks prior to the DD task
will change to forward dated, even though these tasks relationship to the DD did not change.




Changes

None

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.