Max Event Level Was Reached During Events Execution

(Doc ID 1326163.1)

Last updated on JULY 09, 2017

Applies to:

Oracle Agile PLM Framework - Version 9.3.0.2 and later
Information in this document applies to any platform.
***Checked for relevance on 02-Mar-2015***

Goal

What does "Event Maximum Nested Levels Allowed" mean and how to resolve the problem of "Max event level was reached" like below.


com.agile.util.exception.CMAppException: Max event level was reached. To prevent possible infinite loop, the action is stopped.
at com.agile.soa.event.eventmgr.EventMgr.setEventTriggerCount(EventMgr.java:440)
at com.agile.soa.event.eventmgr.EventMgr.invokeEventHandlers(EventMgr.java:233)
at com.agile.soa.event.eventmgr.EventMgrSessionBean.sendPostEvent(EventMgrSessionBean.java:194)
at com.agile.soa.event.eventmgr.EventMgrSessionBean_naafhr_EOImpl.sendPostEvent(EventMgrSessionBean_naafhr_EOImpl.java:6880)
at com.agile.pc.cmserver.event.CMBatchEvent.processSOAEvents(CMBatchEvent.java:348)
at com.agile.pc.cmserver.base.TransactionInfo.afterCompletion(TransactionInfo.java:335)

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms