My Oracle Support Banner

Does ASCP Consider Changeover Times Between The Same Setup Types? (Doc ID 1330752.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal


We have a resource that needs setup of 16 hours after every 100kg of activity. Added changeover time for a setup type as both the from and to, and assigned to the routing.
After collections we see that the changeover time of 16 hrs is collected.
After the plan run, we have multiple planned orders of 100kg but ASCP is not seeing the setup/changeover time required between planned orders.
Is it intended functionality that the duration can only be 0 for the same from/to setup type?


Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.