Pert Chart Layout in Serv Request are Different from Tasks in the Prov Plan
(Doc ID 1333478.1)
Last updated on MARCH 10, 2019
Applies to:
Oracle Communications MetaSolv Solution - Version 6.0.15 and laterInformation in this document applies to any platform.
Symptoms
Enhancement Details:
Users are complaining that the layout of pert charts defined in the provisioning plans are not being properly applied when the prov plan is used in a PSR order.
Replication Steps
--------------------
Create PSR orders and use appropriate provisioning plans. The pert chart for the resulting tasks do not follow the layout in the Provisioning Plan used.
Impact
--------
This creates difficulties to identify tasks for the orders.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |