Acceptable Early Days Functionality Not Working in Constrained plan (Doc ID 1347109.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.
***Checked for relevance on 11-MAR-2015***

Symptoms

Define item with acceptable early days value. 
Run Constrained ASCP plan and find item has reschedule message to move to a date that is within the acceptable early days value.

If running a UN-constrained plan notice the acceptable early days value IS respected.

Changes

No changes

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
 Per development in Enhancement 1064672 from FY 1999  and <bug 12809858> Development states: "HLS does not look at acceptable early days during scheduling"