Planned Orders Not Created When Using MPS Supply Schedule and Forecast Demand (Doc ID 1362908.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Checked for relevancy 16-May-2013

Can we use a supply schedule and have a demand schedule that will also explode and plan further supplies?

MPS supply schedule qty = 5
Forecast or MDS Demand qty = 50

Want to see the firm planned order of 5
AND
also another planned order of 45 to satisfy the forecast/MDS demand


Solution