How to Give a Large Number of Activities an Actual Start via Global Change (Doc ID 1378438.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera P6 Professional Project Management - Version: 5.0 and later    [Release: 5.0 and later]
Information in this document applies to any platform.

Goal

The goal of this document is to give a large number of activities an Actual Start without having to manually check the Actual Start box.


Solution